CLIA inspection: what happens, how often, and how to prepare

Watch the video1:21 on YouTube, with captions

Short answer

Laboratories with a Certificate of Compliance are inspected by State Agency surveyors every two years, and accredited laboratories by their accreditation organization. Waived and PPM sites aren't inspected routinely, and complaint surveys are unannounced.

A CLIA inspection, or survey, checks that a laboratory meets 42 CFR Part 493. State Agency surveyors inspect laboratories with a Certificate of Compliance every two years, accreditation organizations inspect accredited laboratories, and waived and PPM sites are not inspected routinely. Most citations come from records that can't be produced, not from work that wasn't done.

Reviewed 16 Nov 2026 against the sources linked below. General information, not regulatory or legal advice.

Who inspects, and how often

CertificateInspected byHow often
Certificate of WaiverNone routinelyMay be surveyed after a complaint or to collect information about waived testing
Provider-performed microscopy (PPM)None routinelyMay be sampled or surveyed after a complaint
Certificate of ComplianceState Agency surveyors, for CMSAn initial survey, then every two years. The recertification survey falls between 12 and 6 months before the certificate expires
Certificate of AccreditationThe accreditation organizationEvery two years on the organization's schedule. CMS validates a sample of these inspections within 90 days

Laboratories in exempt states (New York and Washington) follow their state program instead.

What happens on the day

  1. Entrance conference. The surveyor explains the plan and asks for the records they need first.
  2. Observation and interviews. CMS describes the survey as interviewing staff, observing current practice and reviewing records. Surveyors follow specimens and results through the laboratory, looking at outcomes rather than paperwork alone.
  3. Records review. The laboratory must allow the inspection and make its records available (42 CFR 493.1773).
  4. Exit conference. The surveyor reviews the findings. It is your chance to present more information and ask questions.

Records surveyors ask to see

  • Policies and the procedure manual, with director approval
  • Personnel files: qualifications, training and competency for each role
  • Proficiency testing results, reviews and corrective action
  • Quality control records
  • Temperature and other storage records
  • Equipment maintenance and function checks
  • Quality assessment reviews
  • Method verification studies and any IQCPs
  • Test reports and the test menu on your certificate

The most-cited findings are records that can't be produced: storage logs, competency assessments and the procedure manual top CMS's 2024 list.

After the survey

  • No deficiencies: the director signs the CMS-2567 and the laboratory receives a letter confirming compliance.
  • Deficiencies: the State Agency sends Form CMS-2567 within 10 working days. Each finding names a D-tag, the regulation and what the surveyor saw.
  • Plan of correction: commonly due within 10 calendar days. It says who is responsible, what was fixed, whether patient results were affected, and what changed to stop it recurring. See how to write one.
  • Condition-level findings are serious and can lead to sanctions. Tennessee's agency, for example, expects evidence of compliance within 45 days of the survey. Standard-level findings must be corrected within 12 months at most.

Preparation checklist

  1. Confirm your certificate type and expiration date, and that the tests you run match the test menu on file.
  2. Run the free readiness check to find gaps against the most-cited requirements.
  3. Put the records above in one binder or folder, with an index of where each one lives.
  4. Check the top citations: storage logs (D5413), competency (D5209), the procedure manual (D5401) and expired materials (D5417).
  5. Check each personnel file for qualifications, training and current competency.
  6. Check proficiency testing: enrolled for each regulated test, results reviewed, and corrective action after any failure. See the PT requirements.
  7. Decide who greets the surveyor and who fetches records, and keep a log of what is requested.
  8. Brief staff: answer honestly, show where procedures are kept, and say so when you need to look something up.

The Inspection Readiness Kit has the full self-audit by subpart, a survey binder index, the personnel file checklist, a survey day sheet and a plan of correction template.

How often are CLIA inspections?

Every two years for laboratories with a Certificate of Compliance or a Certificate of Accreditation. Certificate of Waiver and PPM sites are not inspected routinely, but can be surveyed after a complaint.

Are CLIA inspections announced?

CMS's general policy is to announce routine surveys. Complaint surveys and follow-up revisits are unannounced. Tennessee's survey agency, for example, gives 2 to 14 days' notice for initial, recertification and validation surveys. Accreditation organizations set their own notice rules.

Does a Certificate of Waiver laboratory get inspected?

Not routinely. CMS's manual says a waived laboratory may be investigated after a complaint, and CMS has also visited a small share of waived sites for education. The site must allow an inspection when one happens.

How long do we have to respond to a CMS-2567?

The State Agency has 10 working days after the survey to send Form CMS-2567. The plan of correction is commonly due within 10 calendar days of receiving it; the cover letter gives your date. See how to write a plan of correction.

Sources